Wellington Road Junction Improvements (WRJI) Public Exhibition

Wellington Road Junction Improvements - Design Manual for Roads and Bridges Stage 2 Route Options Assessment - Public Consultation

Wellington Road Junction Improvements is a project focusing on approximately 2km of Wellington Road from Charleston Road North to Craigshaw Drive.

The project will also consider walking/cycling facilities, and buses and freight transport.

The intentions of the project are:    

  • Prioritise sustainable transport along Wellington Road;
  • Support freight movement;
  • Improve access to education along the corridor;
  • Ensure road safety; and
  • Enhance air quality and public health.
Ordnance Survey mapping with a red boundary encompassing the Wellington Road Junction Improvements project extents. Reference to Aberdeen South Harbour Link Road included in light green.

Project Background

The Aberdeen City Region Deal Strategic Transport Appraisal identified opportunity to progress elements of designs from the previous Wellington Road Multi-Modal Corridor Study with the anticipation of achieving additional benefits to the surrounding area.

This is restricted to the length from Charleston Road North to Craigshaw Drive including Souterhead roundabout and Hareness roundabout.

The previous work on the Wellington Road corridor, the Wellington Road Multi-Modal Corridor Study, identified a hybrid package of multi-modal improvements along the length of the corridor.

The design elements brought forward constituted the signalisation of the Souterhead and Hareness Road roundabouts and walking/cycling facilities.

Souterhead Roundabout Google View

Signalisation Feasibility

Traffic modelling was undertaken to understand the impacts if Souterhead roundabout and Hareness roundabout were signalised.

The traffic modelling concluded that signalising the roundabouts had a significant effect on traffic and journey times making it an undesirable option to progress to the next design stage.

Drawings depicting signalisation of the Souterhead and Hareness roundabouts on an ordnance survey map.

Click 'Next' to view the last page.

What's been done?

The Design Manual for Roads and Bridges Stage 2 Route Options Assessment is a concept design phase of a project. At this stage, a long list of options was produced which resulted in a shortlist of options A – F then G – K below.

The image depicts Options A-F for the bus and freight transport improvements. The tables rows are split into seven categories consisting of the following: Segregated two-way flow active travel provision; Pedestrian signalisation of Hareness roundabout; Pedestrian signalisation of Souterhead roundabout; Existing carriageway retained; Existing carriageway retained with a dedicated northbound lane one; Additional northbound bus lane; and Souterhead roundabout bus priority entry lanes.
The image depicts Options G-K for the bus and freight transport improvements. The tables rows are split into seven categories consisting of the following: Segregated two-way flow active travel provision; Pedestrian signalisation of Hareness roundabout; Pedestrian signalisation of Souterhead roundabout; Existing carriageway retained; Existing carriageway retained with a dedicated northbound lane one; Additional northbound bus lane; and Souterhead roundabout bus priority entry lanes.

Each option had an estimated cost associated with it, journey time impact and whole life carbon emissions.

Following careful consideration, Option K was selected as the preferred public transport and freight movement option due to its hybrid approach, lower environmental impact and lower cost.

What's been done?

With an option selected for buses and freight transport, walking/cycling improvements along the length of the project were also considered.

The Design Manual for Roads and Bridges Stage 2 Route Options Assessment investigated the physical constraints on the route to understand potential obstructions and opportunities.

The cross section of the walking/cycling facilities features a 50mm upstand kerb to separate the pavement and cycle track. The cycle track includes a buffer zone when adjacent to Wellington Road.

The image depicts a drawing of the cycle track and pavement separated by a 50mm upstand kerb. The cycle track is 3m wide and allows cyclists to cycle in both directions. The footway is 1.5m and is wide enough for a pedestrian and wheelchair user to pass each other.
The image depicts the first section of the project with a walking and cycling facility on the west side of Wellington Road and the start of a bus lane that starts at the junction with Porche Centre Aberdeen.
The image depicts the walking and cycling facilities on the west side of Wellington Road as it approaches Souterhead roundabout. The bus lane terminates before a signalised pedestrian crossing south of Souterhead roundabout. The walking and cycling facilities continue on the west side of Wellington Road. A combined bus and freight lane begins after Souterhead roundabout and continues north.
The image depicts the walking and cycling facilities continuing on the west side of Wellington Road as the project approaches The Wellington restaurant. The combined bus and freight lane also continues towards The Wellington restaurant.
The image depicts the project approaching Hareness roundabout with the walking and cycling facilities terminating short of Hareness roundabout and crossing over Wellington Road to the east side via a signalised pedestrian crossing. The walking and cycling facility then continues north and crosses Hareness Road with a signalised crossing. Following this, the walking and cycling facility continues north towards Craigshaw Drive. The combined bus and freight lane terminates approximately 125m south of Hareness roundabout.
The image depicts the walking and cycling facility continuing north on the east side of Wellington Road and terminating with at the crossroad with Craigshaw Drive, Wellington Road and Altens Farm Road.

Next steps

The next steps of the project include developing the preferred design and progressing through The Design Manual for Roads and Bridges Stage 3 Scheme Assessment. Preferred option K will be assessed against environmental and engineering issues.

We are also looking at additional walking/cycling improvements to Wellington Road from neighbouring residential communities.

We would welcome your feedback on the preferred option and the additional connections from neighbouring residential communities. See additional connections plan for context.

Additional Connections Plan

The image depicts the Wellington Road Junction Improvement Project boundary on an Ordnance Survey map of Aberdeen. There are 5 connection opportunities which are as follows: Connection Opportunity 1 is additional signage and road markings to improve road safety on the way to Lochside Academy on Wellington Circle. Connection opportunity 2 is to provide an additional bus lane on Langdykes Road. Connection opportunity 3 is to provide a quiet route on Nigg Kirk Road with an upgraded ramp at the end to reduce the gradient and make it more accessible. Walking and cycling facilities on Abotswell Crescent to improve road safety on the way to Wellington Road and Lochside Academy along Redmoss Road. Connection opportunity 4 is a walking and cycling facility on Altens Farm Road behind Aldi to provide an additional connection to Hareness Road and the Aberdeen South Harbour Link Road. Connection opportunity 5 is a shared cycle track on the west side of Wellington Road from Hareness roundabout to Craigshaw Drive.

Aberdeen City Region Deal

The Aberdeen City Region Deal is a partnership between Aberdeen City Council, Aberdeenshire Council, Opportunity North East, other regional partners, the private sector, Scottish Government and UK Government. The Deal is one delivery mechanism for the regional economic strategy and is investing in sector innovation projects and infrastructure to support economic diversification and resilience.

Signed in November 2016, both Governments committed to jointly investing up to £250 million over a 10-year period. These commitments form part of an overarching £826 million funding package for the Aberdeen City Region Deal.

The Wellington Road Junction Improvements project forms part of an overarching £826million funding package for the Aberdeen City Region Deal. Part of this deal is to upgrade the existing transportation links to the recently opened Aberdeen South Harbour.

The image depicts the Aberdeen City Region Deal logo that names the partnership organisations, these are Aberdeen City Council, Aberdeenshire Council, The Scottish Government, UK Government and Opportunity North East

Discover more

Feedback Questionnaire picture
Closed

Feedback Questionnaire

Feedback questions to be completed at your leisure.

Project:Wellington Road Junction Improvements and Aberdeen South Harbour Link Road - Additional Consultation
White map on green background
Closed

Wellington Road Junction Improvements - Pin Map

Feel free to drop a pin and provide comments.

Project:Wellington Road Junction Improvements and Aberdeen South Harbour Link Road - Additional Consultation