Thank you for your interest in Ashgrove Connects Stage 4 of the project has commenced

Thank you for your interest in Ashgrove Connects Stage 4 of the project has commenced

Approval to progress the project was given by the City Growth and Resources Committee of Aberdeen City Council and funding has been secured to progress Stage 4 of the Project. This will involve the development of the Concept Design consulted upon during Stage 2 in 2022 and will include further opportunities for the community and stakeholders to view the design as it develops in more detail.

You can view the Stage 3 and 4 developed design on the pages below. If you need support with this website, please click on the accessibility menu or contact us.

About the project

Email

Timeline

Stage 1: Define

March 2022 - April 2022
During this stage, we want you to share your experiences of using the streets. This will help us to define priorities and establish objectives that the project would seek to achieve. We will also investigate current activity and constraints along the streets through surveys.

Stage 2: Develop

Summer 2022 - Autumn 2022
During this stage, we will use the responses and data collected so far to seek your feedback on objectives and initial design options. This will help us to steer the development of a concept design alongside further technical assessments to be undertaken.

Stage 3: Developing the Design

During this stage, the Stage 2 Concept Design will be developed further. We will use the Stage 2 consultation feedback and technical assessments to inform the emerging design. This will help us to further refine the design in line with the community’s needs as well as determine what can practically be delivered on the ground.

Stage 4: Detail

During this stage, we will prepare all required drawings and information to enable the project to be delivered on the ground. The goal is to finalise the design and prepare the construction information.

Stage 5: Deliver

Please be aware that progression to this stage will be subject to approvals being made and appropriate funding being available. During this stage, we will work alongside the appointed contractor, community, and stakeholders to deliver the project on the ground and ensure construction is managed to minimise any disruption.

News

17 items
pbotuhk0rqqe372uhvkw.jpg

Invite to Stage 4 Events

Ashgrove Connects - Drop-in SessionAshgrove Connects has entered Stage 4 of its journey to enhance Ashgrove Road and Ashgrove Road West. This project is part of a wider city initiative aimed at expand

Posted:
View Update
jrka6kgenwjbutmiy9vj.png

Stage 4 Update

Ashgrove Connects has entered Stage 4 of its journey to enhance Ashgrove Road and Ashgrove Road West. This project is part of a wider city initiative aimed at expanding safe and sustainable travel opt

Posted:
View Update
Image of Ashgrove Road with trees and houses

Invite to Public Engagement Event

We’re moving forward with Stage 3 of Ashgrove Connects, and have now prepared more developed designs for review by residents, businesses and stakeholders like yourself.We encourage you to participate

Posted:
View Update
fe8e96bb-f1a6-49be-9b9f-6f66ddc8b026.png

Your feedback on the Initial Designs and next steps

What did you tell us about the Initial Designs? Since we closed the consultation on the Initial Designs for Ashgrove Connects, we have been busy analysing all your feedback, using this to refine the d

Posted:
View Update
ef391b45-42b8-4b94-9b53-c93f91b387c7.png

Feedback on the initial designs by Sunday

Thank you to everyone who has taken part in the consultation on the initial designs for Ashgrove Connects so far. We've spent time with residents, businesses, pupils and other users of the street

Posted:
View Update
ff9735e2-9f82-4c62-8f8a-905e80faba9a.png

Exploring the designs

Drop in eventsThanks to everyone who took the time to come along to the drop-in events this week at Cairncry Community Centre and Westburn Outdoor Centre to explore the initial designs. It was great t

Posted:
View Update
80a26036-90b4-474c-be20-ed36d74b2dca.png

Drop in events today

Drop in events todayWe've spent the morning at Cairncry Community Centre speaking to members of the community about the initial designs for Ashgrove Connects. We're heading over to Westburn O

Posted:
View Update
fcd4e4a8-5086-4d39-ae54-13f56f628fa8.png

Missed the second webinar? Catch up here

Catch the webinarWe hosted a live webinar on Tuesday as part of the second stage of Ashgrove Connects. This was a great opportunity to present an overview of what we've done so far on the project,

Posted:
View Update
b48300ea-1694-4f9c-8e1a-976611f2728d.png

Developing designs with Cornhill Primary School

We were delighted to spend Wednesday morning with P6 pupils of Cornhill Primary School to present, develop and collect their feedback on the initial designs for Ashgrove Connects. What did pupils tell

Posted:
View Update
2d4455b5-cff0-4e4e-bea3-a4fb22a32602.png

Tell us what you think of the initial designs for Ashgrove Connects

Welcome to the Design Stage of Ashgrove Connects where you can view and feedback on the initial designs which have been developed from what you told us is important to you. Idea for Ashgrove Road West

Posted:
View Update
84469f32-6a97-4edd-b1c6-207aed3067dc.png

What have we found out so far?

Since we closed the initial consultation for Ashgrove Connects, we have been busy analysing all the contributions you shared with us alongside the data we collected from surveys. This news post provid

Posted:
View Update
a927d00d-e310-4e00-b70d-d7c887286a04.png

Fantastic response to the first stage of Ashgrove Connects!

The initial consultation period for Ashgrove Connects has now closed. Thank you to everyone who took part to share their experiences of Ashgrove Road and Ashgrove Road West with us. Fantastic response

Posted:
View Update
f61a68a4-008c-47a2-9730-a3097a0954b7.png

Consultation period extended to Sunday 3rd April

Thank you to everyone who has been involved with Ashgrove Connects so far. As we are still receiving a good number of responses, we have decided to extend the consultation period to Sunday 3rd April.

Posted:
View Update
74789221-f364-4dcc-89ab-8210ed6ce437.jpg

Missed the webinar? Catch up here

Do you want to find out more about Ashgrove Connects? Catch up with the live webinar we held on Wednesday 16th March by clicking here to meet the team, learn more about the project, take a more in d

Posted:
View Update
4702a06b-6a10-4bab-8c26-68177b2acc0a.png

Over 100 responses received so far!

Thank you to everyone who has taken part in Ashgrove Connects so far! We've had over 350 people visit the project website and received over 100 contributions which is fantastic for the first week

Posted:
View Update
5b0bc0cb-934a-463b-8aab-e01cd5a9e490.png

Launching Ashgrove Connects

Ashgrove Connects is a proposed new project to get local people involved in making Ashgrove Road and Ashgrove Road West work better for those who live, work, study and visit here. This is being progre

Posted:
View Update

Meet the team

Aberdeen City Council
Aberdeen City Council

Aberdeen City Council is committed to making improvements across the city that will help provide everyone with more sustainable transport and lifestyle options. Aberdeen City Council will use the data gathered from this platform to inform their decision making and future delivery of the project. For information, please visit: https://www.aberdeencity.gov.uk/

Read Aberdeen City Council privacy policy

Ironside Farrar
Ironside Farrar

Ironside Farrar is committed to delivering sustainable, multi-disciplinary solutions tailored to the unique requirements of each project. As the lead designer for Stage 3 of the Ashgrove Connects project, Ironside Farrar will utilise the data collected from this platform to assist with our design duties in collaboration with Aberdeen City Council. To learn more about our services, please visit: http://www.ironsidefarrar.com/

Read Ironside Farrar privacy policy

Nestrans (Stages 1 & 2)
Nestrans (Stages 1 & 2)

Nestrans is committed to developing and delivering a long-term regional transport strategy and strategic transport improvements that support and improve the economy, environment and quality of life across Aberdeen City and Aberdeenshire. For more information, please visit: https://www.nestrans.org.uk/

Read Nestrans (Stages 1 & 2) privacy policy

Atkins (Stages 1 & 2)
Atkins (Stages 1 & 2)

Atkins is committed to providing sustainable, community-based initiatives to deliver better transport, boost local economies and enhance the liveability of neighbourhoods. Atkins will use the data gathered from this platform to inform their work with Aberdeen City Council. For examples of some of our work, please see here: https://careers.snclavalin.com/landscape-architecture-join

Read Atkins (Stages 1 & 2) privacy policy