Waterline Replacement
J & K Contracting is set to finalize a waterline project encompassing about 1,800 linear feet of construction along NE 14th Street, extending to N. Oak Street, N. Kuney Street, and N. Olive Street. This project, part of the City's planned initiatives, is scheduled to occur from early January through the end of March.
During the course of this project, contractors may intermittently store equipment and waterline materials within the right-of-way, which may result in occasional inconveniences.
Should you have any questions or concerns, please do not hesitate to reach out to the Public Works Department at 263-3510.
[Click here]https://www.abilenecityhall.com/DocumentCenter/View/4397/Bryson-Map) to view an enlarged image of this map.
This webpage is maintained by the City and will serve to keep the community informed of anticipated stages and important dates of this project. All dates are tentative and subject to change as the project progresses. Updates will be made directly to this site. It is encouraged to check back regularly or register for notifications to stay informed.
Stay Informed
Get notified on upcoming engagements and the latest project related news.
Additional Information
Project Updates
Waterline Replacement is finished!
Thank you for your patience and cooperation during construction.
Temporary Water Disruption - March 19, 2024
Effected Area: N. Buckeye Ave to N. Brady and NE 13th Street to NE 21st Street
Temporary Water Shut-off on NE 14th - February 2, 2024
Service disruption from approximately 2pm - 6pm
Waterline Replacement to Begin Soon!
Along NE 14th Street, extending from N. Oak, N. Kuney, and N. Olive streets.
Important Dates
City Commission Awards Contract to J&K Contracting, LC.
City Commission voted to award the contract to J&K Contracting, LC., in the amount of $213,734.60.
Information presented to the City Commission can be viewed here.
Work begins on N. Kuney Street
Waterline replacement work will begin on N. Kuney Street and is anticipated to complete around February 2, 2024, weather permitting.
Works begins on 14th Street and N. Olive Street
Waterline replacement work will begin on both 14th Street and N. Olive Street and is anticipated to complete around March 29, 2024, weather permitting.