Abilene, KS
Aerial view of 14th street extending from N. Oak to N. Olive Streets.

Waterline Replacement

J & K Contracting is set to finalize a waterline project encompassing about 1,800 linear feet of construction along NE 14th Street, extending to N. Oak Street, N. Kuney Street, and N. Olive Street. This project, part of the City's planned initiatives, is scheduled to occur from early January through the end of March.

During the course of this project, contractors may intermittently store equipment and waterline materials within the right-of-way, which may result in occasional inconveniences.

Should you have any questions or concerns, please do not hesitate to reach out to the Public Works Department at 263-3510.

alt_text

alt_text
[Click here]https://www.abilenecityhall.com/DocumentCenter/View/4397/Bryson-Map) to view an enlarged image of this map.

alt_text


This webpage is maintained by the City and will serve to keep the community informed of anticipated stages and important dates of this project. All dates are tentative and subject to change as the project progresses. Updates will be made directly to this site. It is encouraged to check back regularly or register for notifications to stay informed.

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Additional Information

Information about the fund and what it's used for.

Project Updates

Important Dates

13
Nov 2023

City Commission Awards Contract to J&K Contracting, LC.

City Commission voted to award the contract to J&K Contracting, LC., in the amount of $213,734.60.

Information presented to the City Commission can be viewed here.

8
Jan 2024

Work begins on N. Kuney Street

Waterline replacement work will begin on N. Kuney Street and is anticipated to complete around February 2, 2024, weather permitting.

5
Feb 2024

Works begins on 14th Street and N. Olive Street

Waterline replacement work will begin on both 14th Street and N. Olive Street and is anticipated to complete around March 29, 2024, weather permitting.

*See Construction Schedule Map on this page.

23
Apr 2024

Project Complete!