Highlights of the Courthouse Construction Progress

  • Completed brick veneer at the north elevation and continued to west elevation
  • Started installing exterior windows
  • Continued MEP & security overhead at basement level, 1st floor, 2nd floor, & 3rd floor.
  • Started finishing and priming interior walls.
  • Starting underground exterior lighting and pole bases
  • Set HVAC units on the roof
  • Continued sprinkler rough-in
  • Continued interior & exterior framing.
  • Continued exterior blueskin and spray foam insulation
  • Completed TPO roofing
  • Continued site work. demo of asphalt, grading, jail access road, placing curbs, and base pavement.
  • Completed Dick Huff lane/Rt.11 lane widening

View the full July 2025 report for more information and photos of the progress.

Skanska USA Building Inc. serves as the project construction manager for the courthouse project and manages construction on behalf of the County to help make sure that this major construction effort remains on target.

Augusta County courthouse progress July 2025 report, back of courthouse with paved road leading to it

Stay Informed

Get notified on upcoming engagements and the latest project related news.