Verona Courthouse Construction
June 2025 Project Report - Skanska
Highlights of the Courthouse Construction Progress
Construction Highlights for June 2025
- Started brick veneer at the north elevation
- Continued MEP & Security overhead & in-wall rough-in at CMU walls, basement level, 1st floor, 2nd Floor, & 3rd Floor.
- Continued HVAC controls rough in.
- Continued sprinkler rough-in
- Continued security rough-in at CMU Walls, basement, 1st Floor, 2nd floor, & 3rd floor.
- Continued interior & exterior framing on 2nd floor and 3rd floor.
- Continued topping out walls above ceiling with drywall and insulation
- Completed exterior sheathing 1st, 2nd, and 3rd Floor.
- Completed installing Stair 3 and started Stair 2
- Completed fireproofing on the 3rd Floor
- Continued exterior blueskin and spray foam insulation
- Continued TPO roofing
- Continued site work. Underground storm, demo of asphalt,
- Grading, jail access road, and Dick Huff Lane/Rt.11 turn lane widening.
View the full June 2025 report for more information and photos of the progress.
Skanska USA Building Inc. serves as the project construction manager for the courthouse project and manages construction on behalf of the County to help make sure that this major construction effort remains on target.