March 2025 Project Report - Skanska
Verona Courthouse Construction

March 2025 Project Report - Skanska

Highlights of the Courthouse Construction Progress

Construction Highlights for March 2025

  • Completed CMU installation at basement level Interior walls
  • Completed CMU Walls at stair 1 and continuing at shear walls, Secure Elevators, & Staff Elevator.
  • MEP continued overhead & in-wall electrical Rough in at CMU walls, basement level, 1st floor, 2nd Floor, & 3rd Floor.
  • Continued security rough-in at CMU Walls, basement, 1st Floor, and second floor
  • Completed 2nd Floor Concrete Slab.
  • Continued concrete prep work at 3rd floor slab
  • Started Interior & Exterior Framing on 1st & Second Floors
  • Started exterior sheathing 1st & 2nd Floors
  • Completed Erecting Steel at Sequence(s) 5,6,7
  • Continued welding and detailing for steel
  • Started installing Steel at sequence 8 and Stair 1
  • Completed storm line work adjacent to maintenance building
  • Started installing curbs at south parking lot/roadway
  • Continued Fireproofing of steel 1st, 2nd, & 3rd Floors
  • Continued Exterior & Interior metal framing on 1st floor and Started on 2nd & 3rd Floors

Click to view the full report for more information and photos of the progress.

Skanska USA Building Inc. serves as the project construction manager for the courthouse project and manages construction on behalf of the County to help make sure that this major construction effort remains on target.

March2025 front view of Augusta County courthouse construction in Verona