May 2025 Project Report - Skanska
Verona Courthouse Construction

May 2025 Project Report - Skanska

Highlights of the Courthouse Construction Progress

Construction Highlights for May 2025

  • Continued CMU Walls at stair 2, shear walls, 3rd floor Detention area, Secure Elevators, & Staff Elevator.
  • Continued MEP & Security overhead & in-wall rough-in at CMU walls, basement level, 1st floor, 2nd Floor, & 3rd Floor.
  • Continued HVAC Controls rough in LL, 1st, & 2nd Floors.
  • Continued Sprinkler rough-in at LL and 1st floor
  • Continued security rough-in at CMU Walls, basement, 1st Floor, 2nd floor, & 3rd floor.
  • Continued Interior & Exterior Framing on 2nd Floor and 3rd floor.
  • Started Topping out Walls above ceiling with drywall and insulation
  • Continued exterior sheathing 1st, 2nd, and 3rd Floor.
  • Completed welding and detailing for steel
  • Completed installation of Stair 1 and Started Stair 3
  • Continued Fireproofing on the 3rd Floor
  • Continued Exterior Window Blocking & Installing Brick Ties
  • Started Exterior Blueskin and Spray Foam Insulation
  • Started TPO Roofing

View the full May 2025 report for more information and photos of the progress.

Skanska USA Building Inc. serves as the project construction manager for the courthouse project and manages construction on behalf of the County to help make sure that this major construction effort remains on target.