October 2024 Progress Report - Skanska
Verona Courthouse Construction

October 2024 Progress Report - Skanska

Highlights of the Courthouse Construction Progress

October 2024 Progress Report - Skanska

Construction highlights for October:

  • Installed elevator pistons with crane at lower level
  • Removed large light pole and base at west corner of site
  • Continued installing aggregate piers at upper level
  • Poured concrete for last section of retaining wall and stripped forms
  • Poured concrete for elevator pits and stripped forms
  • Poured concrete for loading dock walls
  • Continued installing rebar/forms and pouring lower level footings
  • Began installing rebar for upper level footings
  • Continued installing CMU walls for stairwells, sally ports, and elevator shafts
  • Continued underground electrical and plumbing installation
  • Continued electrical and plumbing rough-in at CMU walls
  • Installed security conduit at CMU walls
  • Applied waterproofing and backfilled retaining walls
  • Hauled excess soil off site

View the report for photos of the progress!

Skanska USA Building Inc. serves as the project construction manager for the courthouse project and manages construction on behalf of the County to help make sure that this major construction effort remains on target.

Oct 2024 courthouse construction

Stay Informed

Get notified on upcoming engagements and the latest project related news.