September 2025 Project Report - Skanska
Verona Courthouse Construction

September 2025 Project Report - Skanska

Highlights of the Courthouse Construction Progress

Construction Highlights for Sept 2025

  • Continued Brick Vineer
  • Continued Installing Exterior Windows
  • Continued Installing FRP at exterior
  • Continued Framing Drywall Ceilings and Bulkheads
  • Continued MEP & Security overhead at basement level, 1st floor, 2nd Floor, & 3rd Floor.
  • Continued Telecommunication cabling
  • Started Audio Visual Cabling
  • Continued finishing and priming interior walls.
  • Continued Tile work in bathrooms
  • Continued underground exterior lighting and pole bases
  • Continued Sprinkler rough-in
  • Continued Interior & Exterior Framing.
  • Completed Exterior Blueskin and Spray Foam Insulation
  • Continued Roof Coping and Standing Seam Roofing
  • Continued Site work. Demo of asphalt, Grading, Jail Access Road, placing curbs, and base pavement.

View the full Sept 2025 report for more information and photos of the progress.

Skanska USA Building Inc. serves as the project construction manager for the courthouse project and manages construction on behalf of the County to help make sure that this major construction effort remains on target.

front of courthouse with paved sidewalks completed, Sept 2025