December 2024 Project Report - Skanska
Verona Courthouse Construction

December 2024 Project Report - Skanska

Highlights of the Courthouse Construction Progress

Construction Highlights for December 2024

  • Continued CMU installation at basement level exterior walls
  • Continued CMU installation for stair and elevator shafts at upper level
  • Installed temporary doors in basement
  • Continued underground plumbing at first floor area
  • Installed underground electrical conduit at first floor area
  • Continued electrical and security rough-in in basement
  • Poured concrete slab-on-grade in basement
  • Installed metal decking at first floor
  • Set steel at the upper level for sequence 2
  • Continued welding and detailing for steel
  • Misc. grading and stone placement at first floor area of building pad
  • Continued storm line work adjacent to maintenance building

View the full report for more information and photos of the progress.

Skanska USA Building Inc. serves as the project construction manager for the courthouse project and manages construction on behalf of the County to help make sure that this major construction effort remains on target.

photo of courthouse construction site Dec 2024