November 2024 Project Report - Skanska
Verona Courthouse Construction

November 2024 Project Report - Skanska

Highlights of the Courthouse Construction Progress

Construction Highlights for November

  • Continued installing underground plumbing in basement
  • Continued installing underground electrical conduit in basement, as well as rough-in through CMU walls
  • Security conduit rough-in at CMU walls in basement
  • Placed type 57 stone throughout basement area
  • Continued CMU installation for stairs, elevators, and sally port in basement
  • Continued CMU shear walls and began foundation courses for first floor
  • Poured concrete footings and piers at first floor/upper level, and at south side retaining wall footing
  • Continued backfill of retaining walls
  • Continued installation of telecommunications fiber underground
  • Continued installation of site utilities including storm, sanitary sewer, and water lines
  • Mobilized crane for structural steel sequence 1 – began erecting steel columns at basement level
  • Set steel cross beams for the first floor

View the report for photos of the progress!

Skanska USA Building Inc. serves as the project construction manager for the courthouse project and manages construction on behalf of the County to help make sure that this major construction effort remains on target.

Nov 2024 courthouse construction photo showing progress - foundation being poured and walls started