Louisiana Avenue Regional Detention Basin
Project Update - March 10, 2023
Watch this short video update on the La Avenue Regional Detention Basin Project
Update:
• 140 days in to the project
• 75% of off-site dirt removal complete
• Approximately 6000 loads of dirt removed (roughly 120,000 cubic yards)
• Intake structures installed
• Project is ahead of schedule