Judicial Complex Project
Twenty-Four Week Update
Twenty-Four Week Project Update: Calcasieu Parish Judicial Complex
We are officially 24 weeks into construction of the new Calcasieu Parish Judicial Complex!
Since our last update:
- A temporary sidewalk and ramp have been added to the west side of the Parish Government Building to support safe emergency exits during construction.
- The chiller has been relocated to the new mechanical yard.
- A drainage trench was excavated, and piping has been installed to improve site drainage.
- A few initial grade beam pours have been completed.
- The former parking garage has been completely demolished.
- Crews have finished excavating elevator pits.
We will continue sharing project updates every six weeks. Text “judicial” to 78015 to recieve mobile updates.