A417 Missing Link

Background of the A417 Missing Link

90% of the A417 route is dual carriageway, there is one section that isn’t - the Missing Link. 

c.37,000 vehicles per day climb Crickley Hill (10% gradient), with approx. 10% being HGVs. 

Congestion is frequent at Air Balloon and Cowley roundabouts, collisions and breakdowns are a common occurrence

Rat running through local villages is a further safety issue

We plan to build 3.4 miles (5.5km) of new dual carriageway, which will:

  • improve road safety, 
  • reduce congestion, and 
  • improve connectivity for road users and local communities

The solution

  • Maintaining the existing alignment up Crickley Hill, new section diverts to the east just before the Air Balloon pub
  • Offline section between Ullenwood and Cowley junction
  • Air Balloon and Cowley roundabouts removed
  • Major junction at Shab Hill, for journeys to Birdlip, Cowley, Cheltenham and Oxford 
  • Existing section of A417 converted to walking, cycling and horse riding route
  • False cuttings used to reduce visual impact
  • Two new crossings for Cotswold and Gloucestershire Way walking trails
  • 2020 design changes:
  • altered gradient and removed green bridge
  • Added 37m-wide Glos. Way bridge
  • Removed virtually all retaining structures, 
  • Scheme is unlit to maintain ‘dark skies
  • Working with conservation groups has been at the heart of our landscape-led approach.
  • Crossings have been a key focus of collaborative design sessions
  • Working with our stakeholders and taking them on the journey has been key to developing this scheme.

For more information, please refer to the following documents:

Development Consent Order (DCO) Decision Letter

Public Consultation

Stay Informed

Follow our projects to get notified of upcoming engagements and the latest project related news.