Waterline Replacement
• Bassard Dr – S. Clinton to Darbyshire Dr (existing 6” waterline installed approximately 1947 & is AC)
• Darbyshire Dr – Bassard Dr to Glenwood (existing 6” waterline installed approximately 1947 & is AC)
• Glenwood Dr – S Clinton to Darbyshire Dr (existing 4” waterline installed approximately 1951 & is AC)
• Mayo Dr – Glenwood Dr to Bassard Dr (existing 6” waterline installed approximately 1947 & is AC)

Sanitary & Storm Sewer Rehabilitation: where needed

Lateral Repairs in Right-of-Way: where needed

Pavement Rehabilitation
In addition to the proposed waterline replacements, the city will perform pavement rehabilitation in the entire Darbyshire area. The work will be performed as follows:

Mill & Resurface
Huron Dr
Wyandott Ave
Bassard Dr (Mayo to Darbyshire)

Mill & Resurface with full depth pavement repairs at needed locations
Mayo Dr
Glenwood Dr (Clinton St to Mayo)

Full Depth Reclamation
Glenwood Dr (Mayo to Darbyshire)
Darbyshire Dr (Mayo/Glenwood to Bassard)
Bassard Dr (Clinton to Mayo)

Dates of Last Documented Pavement Rehabilitation
• Bassard Dr – 1 ¼” asphalt overlay in 1992
• Mayo Dr – 2” asphalt overlay in 1969
• Glenwood Dr – 1 ¼” asphalt overlay in 2000
• Wyandotte Ave – 2” asphalt overlay in 1969
• Huron Dr - 2” asphalt overlay in 1969
• Darbyshire Dr - 2” asphalt overlay in 1969

Schematic of Darbyshire Neighborhood Improvements 2023-2024

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Project Updates

Important Dates

21
Jul 2023

Bid Opening

8
Aug 2023

Consideration for Award of Contract before City Council

31
Mar 2024

Substantial Completion: Watermain, Rehabilitation, & Open Cut Lateral Work

30
Jun 2024

Substantial Completion: Pavement

31
Jul 2024

Final Completion