Visit Zencity Homepage
Project

Construction Schedule

Look Ahead (10/30-11/17)

Water Main Project

One Week Look Ahead (10/30-11/3)

  • Monday thru Thursday :
    • Crew #1: Continue Installation of Force Main on Surfside Road (around Cobble Court heading North to Vesper) – Night
  • Friday:
    • Paving – 7am-3pm

Two Week Look Ahead (11/6-11/10)

  • Monday thru Thursday :
    • Crew #1: Continue Installation of Force Main on Surfside Road– Night
  • Friday:
    • Paving – 7am-3pm

Three Week Look Ahead (11/13-11/17)

  • Monday thru Thursday :
    • Crew #1: Continue Installation of Force Main on Surfside Road– Night
  • Friday:
    • Paving – 7am-3pm

Current Road Closures: Surfside Road – CLOSED To Thru Traffic 4 PM – 3 AM (M-THUR), 7 AM- 3PM (FRI)

Please note that this is a projected schedule and will be adjusted accordingly based on Contractor’s actual progress and potential weather cancellations.

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Contact Us

Follow Us