Visit Zencity Homepage
Construction Schedule
Project

Construction Schedule

Look Ahead (12/4-12/22)

Water Main Project

One Week Look Ahead (12/4-12/8)

Construction Hours: M-F, 7AM-4PM
Road Closure Hours: 24/7 on Surfside Rd. & Lily St.

  • Crew #1: Continue Installation of Force Main on Surfside Road – Cross Connection.
  • Crew #1 : Mobilize to Lily Street to commence Force Main Work

Two Week Look Ahead (12/11-12/15)

Construction Hours: M-F, 7AM-4PM
Road Closure Hours: 24/7 on Lily St. and Atlantic Avenue (South Prospect St. to Pleasant St).

  • Crew #1: Continue Installation of Force Main on Lily
  • Crew #2 : Commence Installation of Force Main on Atlantic.

Three Week Look Ahead (12/18-12/22)

Construction Hours: M-F, 7AM-4PM
Road Closure Hours: 24/7 on Lily St. and Atlantic Avenue (South Prospect St. to Pleasant St).

  • Crew #1: Continue Installation of Force Main on Lily
  • Crew #2 : Commence Installation of Force Main on Atlantic.

Please note that this is a projected schedule and will be adjusted accordingly based on Contractor’s actual progress and potential weather cancellations.

Atlantic Ave. and Lily Street Closure Maps

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Contact Us

Follow Us