Wilmington/I-675 Improvement Plan

The I-675 and Wilmington Pike Interchange, a vital transportation hub serving Centerville, Sugarcreek Township, and Greene County, has become a cornerstone for the region's economic vitality. Connecting residents with major employers such as Wright-Patterson Air Force Base, Sinclair College, and Premier Health, as well as popular destinations like the Cornerstone Development shopping and entertainment district, this interchange plays an essential role in sustaining and expanding the local economy. However, growing traffic congestion in the area has brought forth the need for targeted infrastructure improvements to enhance safety, efficiency, and long-term accessibility.

In light of these challenges and opportunities, local government and planning experts are working to develop solutions that will meet not only today’s transportation demands but also support future growth and development. To ensure that these measures truly reflect the priorities and needs of those most impacted, input from residents, businesses, and community stakeholders will be at the forefront of this deliberative process. This project represents a critical chance for the public to shape the future of the region’s roadways and strengthen the area's capacity to thrive, and your feedback will directly inform the decision-making process.

Funding to Date:
The Wilmington Pike / Clyo Road phase of construction received $2.97 million from the Miami Valley Regional Planning Commission (MVRPC) in federal funding.

  • Survey, Stage 1 Design and Environmental Work cost $3.75 million in CDs and local spending
  • Interchange Feasibility Study and Alternative Evaluation Report cost $792,000 in TRAC and local funding.
  • The Influence Area Feasibility Study cost $619,000 in local funding.

The total cost of the project is currently estimated at $71 million. Additional funding will be sought in the coming years.

Construction Timing
Necessary studies have been completed. Staff anticipate Ohio Department of Transportation approval of the selected alternate will come in spring 2025. The project has been broken into five phases. Construction of the Wilmington Pike / Clyo Road phase is expected to begin in 2030.

Community Benefit
The I-675 and Wilmington Pike Interchange serves major employment and commercial centers, including Wright-Patterson Air Force Base, Sinclair College, and Premier Health, as well as the Cornerstone Development shopping and entertainment district. Growing congestion issues, along with continued opportunity for economic growth in the area, has prompted local interests to consider improvements to both the interchange and the local roadway network to support the City of Centerville, Sugarcreek Township, and Greene County.

map

Opportunities to Engage

Stay Informed

Get notified on upcoming engagements and the latest project related news.

"Your voice matters—share your insights online to help shape the future of this project, a vital connection supporting Centerville."
Pat Turnbull
Pat Turnbull
Public Works Director

Project Phases

Public Information Sessions

May 2025 - August 2025

Environmental Review and Approvals

September 2025 - March 2026

Community Feedback and Design Refinement