
One Week Look Ahead (9/11-9/15)
- Monday thru Friday : Start of the New Season
- Crew #1: Remobilize & Continue Installation of Force Main on Surfside
Road ( Starting Work around Tashma Lane) – Night
Two Week Look Ahead (9/18-9/22)
- Monday thru Friday :
- Crew #1: Continue Installation of Force Main on Surfside Road – Night
Three Week Look Ahead (9/25-9/29)
- Monday thru Friday :
- Crew #1: Continue Installation of Force Main on Surfside Road – Night
Construction Hours:
- Monday – Thursday 4 PM – 3AM on Surfside
- Friday 7 AM – 3 PM on Surfside
Current Road Closures: Surfside Road – CLOSED To Thru Traffic 4 PM – 3 AM (M-THUR), 7 AM- 3PM (FRI)
Please note that this is a projected schedule and will be adjusted accordingly based on Contractor’s actual progress and potential weather cancellations.
Stay Informed
Get notified on upcoming engagements and the latest project related news.
Contact Us
Email sewer@nantucket-ma.gov