Construction Schedule
Look ahead (1/22-2/09)
Capacity Management Operations and Maintenance (CMOM) Repair Replacement Project
One Week Look Ahead (01/22-01/26)
Construction Hours: M-F, 7AM-4PM
- Continue repair project on King Street (Siasconset)
Two Week Look Ahead (01/29-02/02)
Construction Hours: M-F, 7AM-4PM
Road Closure: Due to East Dover Street being such a narrow street, traffic will be detoured to the right on Orange Street and then left on Union Street to return to the East Dover Street / Union Street intersection.
- Begin repair project on East Dover Street
Three Week Look Ahead (02/05-02/09)
Construction Hours: M-F, 7AM-4PM
Road Closure: Due to East Dover Street being such a narrow street, traffic will be detoured to the right on Orange Street and then left on Union Street to return to the East Dover Street / Union Street intersection.
- Continue repair project on East Dover Street
Please note that this is a projected schedule and will be adjusted accordingly based on Contractor’s actual progress and potential weather cancellations.
Stay Informed
Get notified on upcoming engagements and the latest project related news.