Week of January 22-January 26
- Friday 01/26/2024 – Begin watermain installation on Webster Avenue. Full road closure no thru traffic. Resident access only.
Week of January 29-February 2
- Crew #01 - Monday 01/29 to 01/31/2024 – Install Watermain on Webster Avenue. Full road and sidewalk closure. No thru traffic.
- Crew #01 - Thursday 02/01 to Friday 02/02/2024 – Continue Watermain Installation on Monohansett from Webster to Okorwaw Avenue
- Crew #02 – Monday 01/29 to Thursday 02/01/2023 – Install Water Services on Nobadeer Way
Week of February 5-February 9
- Crew #01 – Monday 02/05 through Friday 02/09/2024 – Install Watermain Monohansett Road between Webster and Okorwaw Avenue
- Crew #01 – Friday 02/09/2024 – TS&V Connection at Airport Property at the end of Okorwaw Avenue
Week of February 12-February 16
- Crew #01 – Monday 02/12 to Wednesday 02/14/2024 – Install Watermain on Okorwaw Avenue between Airport and Monohansett Intersection. Full road closure. Resident access only.
- Crew #01 – Thursday 02/15 and Friday 02/16/2024 – Install Watermain on Monohansett Dead end road to Okorwaw Intersection. Full road closure. Resident access only.
Stay Informed
Get notified on upcoming engagements and the latest project related news.