
One Week Look Ahead (11/20-11/22)
- Monday thru Wednesday : 7 AM - 4 PM
- Crew #1: Continue Installation of Force Main on Surfside Road - **Working from Hooper Farm Road to Hatikva Way. One Lane Alternating. **
- Thursday & Friday: NO WORK - OFF FOR HOLIDAYS*
Two Week Look Ahead (11/27-12/1)
- Monday thru Friday : ALL DAY
- Crew #1: Continue Installation of Force Main on Surfside Road - **Cross Connection. This will be a 24 HR. Shut Down. **
Three Week Look Ahead (12/4-12/8)
- Monday thru Friday : ALL DAY
- Crew #1: Continue Installation of Force Main on Surfside Road - **Cross Connection. This will be a 24 HR. Shut Down. **
NOTE: 24-hour shut down may continue through 12/8, but could end sooner. We will continue to provide updates as the work progresses.
- Crew #1: Continue Installation of Force Main on Surfside Road - **Cross Connection. This will be a 24 HR. Shut Down. **
Please note that this is a projected schedule and will be adjusted accordingly based on Contractor’s actual progress and potential weather cancellations.
Stay Informed
Get notified on upcoming engagements and the latest project related news.
Contact Us
Email sewer@nantucket-ma.gov