Construction Schedule
Project

Construction Schedule

Look Ahead (10/30-11/17)

Water Main Project

One Week Look Ahead (10/30-11/3)

  • Monday thru Thursday :
    • Crew #1: Continue Installation of Force Main on Surfside Road (around Cobble Court heading North to Vesper) – Night
  • Friday:
    • Paving – 7am-3pm

Two Week Look Ahead (11/6-11/10)

  • Monday thru Thursday :
    • Crew #1: Continue Installation of Force Main on Surfside Road– Night
  • Friday:
    • Paving – 7am-3pm

Three Week Look Ahead (11/13-11/17)

  • Monday thru Thursday :
    • Crew #1: Continue Installation of Force Main on Surfside Road– Night
  • Friday:
    • Paving – 7am-3pm

Current Road Closures: Surfside Road – CLOSED To Thru Traffic 4 PM – 3 AM (M-THUR), 7 AM- 3PM (FRI)

Please note that this is a projected schedule and will be adjusted accordingly based on Contractor’s actual progress and potential weather cancellations.