One Week Look Ahead (9/11-9/15)
- Monday thru Friday : Start of the New Season
- Crew #1: Remobilize & Continue Installation of Force Main on Surfside
Road ( Starting Work around Tashma Lane) – Night
Two Week Look Ahead (9/18-9/22)
- Monday thru Friday :
- Crew #1: Continue Installation of Force Main on Surfside Road – Night
Three Week Look Ahead (9/25-9/29)
- Monday thru Friday :
- Crew #1: Continue Installation of Force Main on Surfside Road – Night
Construction Hours:
- Monday – Thursday 4 PM – 3AM on Surfside
- Friday 7 AM – 3 PM on Surfside
Current Road Closures: Surfside Road – CLOSED To Thru Traffic 4 PM – 3 AM (M-THUR), 7 AM- 3PM (FRI)
Please note that this is a projected schedule and will be adjusted accordingly based on Contractor’s actual progress and potential weather cancellations.