Water Main Expansion

  • Project Timeline: Fall 2023 - Fall 2025
  • Project Manager: Water Department Director Mark Willett
  • Design Engineer: James Drake, CDM Smith, Inc.
  • Resident Project Representative: Ziad Kary, Environmental Partners Group, Inc.

This project is the expansion of a Town Water Main as part of the Town’s voluntary efforts to address potential PFAS contamination in private wells west of the Airport. This project is technically separate from the roadway reconstruction, drainage, and multi-use path projects underway however it does overlap on the roadway projects on Lovers Lane, Okorwaw Avenue and Monohansett Road, Phase 2, 3 and 4 respectively. Specifically, this water main project includes the remaining portions of Lovers Lane and Skyline Drive, and all of Webster Road, and Nobadeer Way.

The water main project is funded by Massachusetts’ Department of Environmental Protection’s (MADEP) State Revolving Fund (SRF). The Town’s $8.3M application for the SRF was accepted and the project was placed on the MADEP’s SRF Intended Use Plan in February 2022. 2022 ATM Article 10 – New Water Main West of Airport approved $9.0M debt exclusion and 2022 ATE Ballot Question 13 approved the $9.0M debt exclusion (approved 1,738 Yes, 496 No, 140 Blank).

Because the timeline for use of the SRF funding is faster than the existing roadway reconstruction projects (see Guide to SRF Financing), the Water Main Expansion Project is considered Phase 1 in the sequence of projects. The Water Main Expansion Project overlaps multiple Surfside area roads intended for roadway reconstruction, drainage and mixed-use path upgrades, therefore the Project Team advocates accelerating the schedule of the roadway reconstruction projects to address paving the roads following the Water Main Expansion project.

In accordance with the Massachusetts Department of Environmental Protection’s State Revolving Fund Program, the Town’s water main expansion project is being bid under Ch.30 Section 39M

DWSRF Project No. 7011

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Mark Willett
Water Department Director

Important Information

Last updated: October 2023

Project Updates

Important Dates

6
May 2023

2023 Annual Town Meeting

Article 96 Real Estate Acquisition: Easements in Skyline Drive, Webster Road, Portions of Monohansett Road and Okorwaw Avenue for Water Main Extension Project was approved at the May 6, 2023 Annual Town Meeting.

1
Jun 2023

Re-Post Bid (original posting 02/25/2023)

8
Jun 2023

Voluntary Pre-Bid Conference

29
Jun 2023

Bid opening

Posting requirement: 4 weeks from posting.

2
Aug 2023

Select Board Meeting/Vote

4
Aug 2023

Contract Execution

08/31/2023 deadline for contract execution per MassEP.

16
Aug 2023

Construction Services Contract Award

Resident Project Representative contract awarded to Environmental Partners Group, Inc.

EGP, Inc. Service Contract
EGP, Inc. Service Contract (Exhibit B)
EGP, Inc. Service Contract (Exhibits C-E)

31
Aug 2023

Construction Contract

Construction Contract awarded to CC Construction, Inc.
CC Construction Contract

30
Oct 2023

Anticipated Construction Start

October 30, 2023

Anticipated start of Phase 1 construction on Monhansett Road

16
Jan 2024

Construction Begins

Construction of Phase 1 begins on Nobadeer Way.