Water Main Expansion

Construction Schedule

Three Week Look Ahead (1/22-2/16)

Week of January 22-January 26

  • Friday 01/26/2024 – Begin watermain installation on Webster Avenue. Full road closure no thru traffic. Resident access only.

Week of January 29-February 2

  • Crew #01 - Monday 01/29 to 01/31/2024 – Install Watermain on Webster Avenue. Full road and sidewalk closure. No thru traffic.
  • Crew #01 - Thursday 02/01 to Friday 02/02/2024 – Continue Watermain Installation on Monohansett from Webster to Okorwaw Avenue
  • Crew #02 – Monday 01/29 to Thursday 02/01/2023 – Install Water Services on Nobadeer Way

Week of February 5-February 9

  • Crew #01 – Monday 02/05 through Friday 02/09/2024 – Install Watermain Monohansett Road between Webster and Okorwaw Avenue
  • Crew #01 – Friday 02/09/2024 – TS&V Connection at Airport Property at the end of Okorwaw Avenue

Week of February 12-February 16

  • Crew #01 – Monday 02/12 to Wednesday 02/14/2024 – Install Watermain on Okorwaw Avenue between Airport and Monohansett Intersection. Full road closure. Resident access only.
  • Crew #01 – Thursday 02/15 and Friday 02/16/2024 – Install Watermain on Monohansett Dead end road to Okorwaw Intersection. Full road closure. Resident access only.