One Week Look Ahead (11/20-11/22)
- Monday thru Wednesday : 7 AM - 4 PM
- Crew #1: Continue Installation of Force Main on Surfside Road - **Working from Hooper Farm Road to Hatikva Way. One Lane Alternating. **
- Thursday & Friday: NO WORK - OFF FOR HOLIDAYS*
Two Week Look Ahead (11/27-12/1)
- Monday thru Friday : ALL DAY
- Crew #1: Continue Installation of Force Main on Surfside Road - **Cross Connection. This will be a 24 HR. Shut Down. **
Three Week Look Ahead (12/4-12/8)
- Monday thru Friday : ALL DAY
- Crew #1: Continue Installation of Force Main on Surfside Road - **Cross Connection. This will be a 24 HR. Shut Down. **
NOTE: 24-hour shut down may continue through 12/8, but could end sooner. We will continue to provide updates as the work progresses.
- Crew #1: Continue Installation of Force Main on Surfside Road - **Cross Connection. This will be a 24 HR. Shut Down. **
Please note that this is a projected schedule and will be adjusted accordingly based on Contractor’s actual progress and potential weather cancellations.