Construction Schedule

Look Ahead: 9/11-9/29 Schedule

Water Main Project

One Week Look Ahead (9/11-9/15)

  • Monday thru Friday : Start of the New Season
  • Crew #1: Remobilize & Continue Installation of Force Main on Surfside
    Road ( Starting Work around Tashma Lane) – Night

Two Week Look Ahead (9/18-9/22)

  • Monday thru Friday :
  • Crew #1: Continue Installation of Force Main on Surfside Road – Night

Three Week Look Ahead (9/25-9/29)

  • Monday thru Friday :
  • Crew #1: Continue Installation of Force Main on Surfside Road – Night

Construction Hours:

  • Monday – Thursday 4 PM – 3AM on Surfside
  • Friday 7 AM – 3 PM on Surfside

Current Road Closures: Surfside Road – CLOSED To Thru Traffic 4 PM – 3 AM (M-THUR), 7 AM- 3PM (FRI)

Please note that this is a projected schedule and will be adjusted accordingly based on Contractor’s actual progress and potential weather cancellations.