Construction Schedule

Look Ahead (12/4-12/22)

Water Main Project

One Week Look Ahead (12/4-12/8)

Construction Hours: M-F, 7AM-4PM
Road Closure Hours: 24/7 on Surfside Rd. & Lily St.

  • Crew #1: Continue Installation of Force Main on Surfside Road – Cross Connection.
  • Crew #1 : Mobilize to Lily Street to commence Force Main Work

Two Week Look Ahead (12/11-12/15)

Construction Hours: M-F, 7AM-4PM
Road Closure Hours: 24/7 on Lily St. and Atlantic Avenue (South Prospect St. to Pleasant St).

  • Crew #1: Continue Installation of Force Main on Lily
  • Crew #2 : Commence Installation of Force Main on Atlantic.

Three Week Look Ahead (12/18-12/22)

Construction Hours: M-F, 7AM-4PM
Road Closure Hours: 24/7 on Lily St. and Atlantic Avenue (South Prospect St. to Pleasant St).

  • Crew #1: Continue Installation of Force Main on Lily
  • Crew #2 : Commence Installation of Force Main on Atlantic.

Please note that this is a projected schedule and will be adjusted accordingly based on Contractor’s actual progress and potential weather cancellations.