Visit Zencity Homepage
Construction Schedule
Project

Construction Schedule

Look Ahead (12/18/23-1/5/24)

Water Main Project

One Week Look Ahead (12/18-12/22)

Construction Hours: M-F, 7AM-4PM
Road Closure Hours: 24/7

  • Crew #1: Continue Installation of Force Main on Lily Street
  • Crew #2 : Commence Installation of Force Main on Atlantic Avenue

Two Week Look Ahead (12/11-12/15)

Construction Hours: M-F, 7AM-4PM
Road Closure Hours: 24/7

  • Crew #1: Continue Installation of Force Main on Lily Street
  • Crew #2 : Continue Installation of Force Main on Atlantic Avenue

Three Week Look Ahead (12/18-12/22)

Construction Hours: M-F, 7AM-4PM
Road Closure Hours: 24/7

  • Crew #1: Continue Installation of Force Main on Lily Street
  • Crew #2 : Continue Installation of Force Main on Atlantic Avenue

Please note that this is a projected schedule and will be adjusted accordingly based on Contractor’s actual progress and potential weather cancellations.

Road Closure Map

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Contact Us

Follow Us