Visit Zencity Homepage
Construction Schedule
Project

Construction Schedule

Look Ahead: 9/11-9/29 Schedule

Water Main Project

One Week Look Ahead (9/11-9/15)

  • Monday thru Friday : Start of the New Season
  • Crew #1: Remobilize & Continue Installation of Force Main on Surfside
    Road ( Starting Work around Tashma Lane) – Night

Two Week Look Ahead (9/18-9/22)

  • Monday thru Friday :
  • Crew #1: Continue Installation of Force Main on Surfside Road – Night

Three Week Look Ahead (9/25-9/29)

  • Monday thru Friday :
  • Crew #1: Continue Installation of Force Main on Surfside Road – Night

Construction Hours:

  • Monday – Thursday 4 PM – 3AM on Surfside
  • Friday 7 AM – 3 PM on Surfside

Current Road Closures: Surfside Road – CLOSED To Thru Traffic 4 PM – 3 AM (M-THUR), 7 AM- 3PM (FRI)

Please note that this is a projected schedule and will be adjusted accordingly based on Contractor’s actual progress and potential weather cancellations.

Detour Map

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Contact Us

Follow Us