Denton, TX
Construction Progress
Denton Solid Waste Fleet

Construction Progress

Achievements and Next Steps

ACHIEVEMENTS:
Contractor Mobilization
Geotechnical Testing Contract Executed
Tilt wall planning meeting
Grade beams complete
Casting beds complete

NEXT STEPS:
Utilities
Tilt wall panels poured
Vertical construction

Graphic of foundation being laid

Stay Informed