Denton, TX
Continued Basin Rejuvenation
Lake Lewisville Water Treatment Plant Sludge Improvements

Continued Basin Rejuvenation

Basin 3 is complete.

Basin 3 is complete. For Basin 4, surface preparation is finished, and coating is underway, though it was slightly delayed due to cold temperatures. The Electrical Equipment Rack installation is done, with wiring still to be completed.

Stay Informed

Get notified on upcoming engagements and the latest project related news.