Visit Denton, TX Homepage
Bridge Deck Rebar (Ready for Concrete!)
Project

Detour/Closure Update! April 2026

Hickory Creek Road Phase 3

Contact Us

Call 1-866-555-1234

Detour! Hickory Creek Road & Riverside Drive Closures

A City of Denton map announcing road closures on Hickory Creek Road and Riverpass Drive. The map highlights closures on Hickory Creek Road between Riverpass Drive and Waterside Place, and on Riverpass Drive between Hickory Creek Road and Riverchase Trail. Red dashed boxes labeled “Road Closed” mark closure points. Blue arrows show temporary traffic flow along Waterside Place and Baybrooke Drive. Text on the left states that work begins April 27, 2026, with anticipated completion on July 31, 2026, and that driveway access will be maintained. The City of Denton logo appears in the bottom left corner.

DETOUR !!

WHAT IS HAPPENING? - Hickory Creek Road and Riverpass Drive are temporarily being re-routed to/from Waterside Place and Riverchase Trail.

WHY ARE WE BEING DETOURED?
In addition to the new Hickory Creek Road and bridges, the existing Hickory Creek Road is being realigned and reconstructed from Riverpass Drive back Waterside Place.
There is a planned road closure along Hickory Creek Road and Riverpass. This closure will be ongoing for a couple months.

WHEN? - Please watch for Changeable Message Signs on Hickory Creek Road and Riverpass Drive. Weather has been impacting planned activities.

WHAT ELSE IS HAPPENING?
The BRIDGE is about to get the FIRST DECK POUR. The bridge is being built and poured in phases/sections and this is the FIRST pour.

SCHEDULE?
The project has experienced some schedule set backs. The schedule is being evaluated for time saving opportunities. The road should be opened to traffic in early 2027.