Milam Creek Gravity Sewer and Lift Station
The Milam Creek Project is one of the final stages of the I-35 corridor utility relocation efforts. The project will relocate and add wastewater lines between Highway 77 and Ganzer Road. In addition, a new lift station will be constructed at the intersection of Ganzer Road and East I-35 Frontage Road. This effort will not only support TxDOT's I-35 widening it was also designed/upgraded to support future development in the area.
Project Location: The project will relocate and add wastewater lines between Highway 77 and Ganzer Road. In addition, a new lift station will be constructed at the intersection of Ganzer Road and East I-35 Frontage Road.
Stay Informed
Get notified on upcoming engagements and the latest project related news.

Project Updates
Active Construction
Construction has begun and the force main is moving along quite well.
PUB & Council Set
PUB 4/15 & Council 4/16.
Moving to PUB & Council
PUB & Council later this Month with Contract Award around the corner.
Bidding Opening this Month
Bidding will open this month for 30 days.
Moving Forward towards Solicitation
We have received positive movement on acquiring needed easements to let half of the project.
Update on Easements
Discussions continue to resolve issues with property owners to acquire the easements needed.
Easement Updates
The City is still talking with property owners to acquire the needed easements.
Easements Still needed
City of Denton and it's authorized representatives are working diligently to get these easements.
Movement on Easements
Majority of the easements are being worked.
Awaiting Easements
Several property owners are not willing to give easements to the City. The City continues to reach out to property owners to reach settlement to move the project forward.
Offer Letters Have Been Sent
Offer letters have been sent to landowners.
ROW negotiations still in progress
Due to the complexity of the right of ways and the scale of the project, this process is taking longer than expected.
Right of Way Acquisition
All planning and design are complete.
Planning and Design Complete!
Our team has completed the planning and design!
Easement Acquisition
The team has been working hard on obtaining easements; once all easements have been obtained we will move forward with advertise and bid.
Design Review Update
The team just completed 90% design review and approval; 100% plans are currently being drawn finalized.