Milam Creek Gravity Sewer and Lift Station

The Milam Creek Project is one of the final stages of the I-35 corridor utility relocation efforts. The project will relocate and add wastewater lines between Highway 77 and Ganzer Road. In addition, a new lift station will be constructed at the intersection of Ganzer Road and East I-35 Frontage Road. This effort will not only support TxDOT's I-35 widening it was also designed/upgraded to support future development in the area.

Project Location: The project will relocate and add wastewater lines between Highway 77 and Ganzer Road. In addition, a new lift station will be constructed at the intersection of Ganzer Road and East I-35 Frontage Road.

Map of relocation area

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Shawn Messick, EIT
Shawn Messick, EIT
Construction Projects Manager Shawn.Messick@cityofdenton.com

Project Updates

16 items

Active Construction

Construction has begun and the force main is moving along quite well.

View Update

PUB & Council Set

PUB 4/15 & Council 4/16.

View Update

Moving to PUB & Council

PUB & Council later this Month with Contract Award around the corner.

View Update

Bidding Opening this Month

Bidding will open this month for 30 days.

View Update

Moving Forward towards Solicitation

We have received positive movement on acquiring needed easements to let half of the project.

View Update

Update on Easements

Discussions continue to resolve issues with property owners to acquire the easements needed.

View Update

Easement Updates

The City is still talking with property owners to acquire the needed easements.

View Update

Easements Still needed

City of Denton and it's authorized representatives are working diligently to get these easements.

View Update

Movement on Easements

Majority of the easements are being worked.

View Update

Awaiting Easements

Several property owners are not willing to give easements to the City. The City continues to reach out to property owners to reach settlement to move the project forward.

View Update

Offer Letters Have Been Sent

Offer letters have been sent to landowners.

View Update

ROW negotiations still in progress

Due to the complexity of the right of ways and the scale of the project, this process is taking longer than expected.

View Update

Right of Way Acquisition

All planning and design are complete.

View Update

Planning and Design Complete!

Our team has completed the planning and design!

View Update

Easement Acquisition

The team has been working hard on obtaining easements; once all easements have been obtained we will move forward with advertise and bid.

View Update

Design Review Update

The team just completed 90% design review and approval; 100% plans are currently being drawn finalized.

View Update