Riney Road East Improvement Project

The purpose of this project is to widen Riney Rd to its full roadway width in coordination with the opening of a new DISD elementary school. The Riney Road East Improvement Project will include two segments of concrete roadway. The first segment to be widen consists of approximately 1310 linear feet of street along the frontage of the G. Roland Vela Soccer Complex. The second segment to be widen consists of 270 linear feet along the frontage of two single family residential lots located on Riney Road.

The project will also consist of a 10-foot-wide concrete hike and bike trail. Once constructed, the hike and bike trail will tie the new DISD elementary school property to the City of Denton Northlakes Park trails system. The hike and bike trail will require a prefabricated pedestrian bridge to cross an existing drainage swale and will connect to a concrete sidewalk East of the softball fields.

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Jesus Perez
Jesus Perez
Construction Projects Manager Jesus.Perez@cityofdenton.com

Project Updates

20 items

Construction Start Date selected by Contractor to be March 16, 2026

Construction Start Date selected by Quality Excavation, LLC to being construction.

View Update

Virtual Community Meeting scheduled for March 2026

Virtual Community Meeting to be held on Thursday, March 05, 2026

View Update

Pre-Construction Meeting held at the Development Services Center

Pre-Construction Meeting held at City Offices

View Update

Construction Contract Awarded to Quality Excavation, LLC.

Construction Contract Awarded

View Update

Competitive Seals Bid are being graded by City Staff

City Staff has received five competitive sealed bidding and is in the process of grading them.

View Update

Bidding Phase for the Project

The Project is now in the Bidding Phase.

View Update

The City is reviewing the 90% complete Project Manual

The City continues to review the submitted Project Manual for completeness and accuracy.

View Update

The Project Manual has been submitted to the City for its review.

The Consultant Engineer has compiled and submitted the Project Manual for the City to review.

View Update

100% Plan Set submitted to the City.

The 100% Plan Set has been submitted to the City.

View Update

Right-of-way Acquisition Process Complete!

City Staff has completed the process of Right-Of-Way acquisition by working with affected homeowners.

View Update

90% Plan Set Review Completed by the City

City Staff in Capital Projects have completed the review of the 90% Plan Set.

View Update

Phase 1 Environmental Site Assessment are being conducted.

The City of Denton has initiated the process for a Phase 1 Environmental Assessment be conducted for the two parcel pieces that are planned to be purchased for the Riney Road East Improvement project.

View Update

Appraisal Reports Completed.

In a team effort between the Capital Projects, Real Estate and the Engineering Consultant the appraisal reports have been finalized and are being prepared.

View Update

Appraisal Reports near Completion

Consultant Engineer nears on the completion of the Appraisal Reports.

View Update

Consultant Engineer continues to work on Plan Set!

Consultant Engineer continues to work on the plan set to be able to submit to the City the 90% plan set in August 2024.

View Update

Right of Way Acquisition Process has started!

The Consultant Engineer has prepared the Surveyor's Exhibits needed to begin the right-of-way acquisition process.

View Update

The 60% Plan Set is being reviewed by both internal and external stakeholders!

The 60% plan set continues to be reviewed by City Staff.

View Update

60% Plan Set submitted to the City.

Binkley & Barfield has submitted their prepared 60% Plan Set for the City to review.

View Update

Binkley & Barfield is working on the project schematic plans.

The Consultant Engineer is busy working on the project schematic plans getting them ready for their submittal in March 2024.

View Update

Design Contract Awarded

On November 14, 2023, the design contract was awarded to Binkley & Barfield, Inc. Binkley & Barfield will be working both with internal and external stakeholders to move forward with the design.

View Update