In June 2025, Tahoe Regional Planning Agency released the following tentative schedule of important dates for the environmental analysis and application process.
Estimated EIS Timeline
In June 2025, Tahoe Regional Planning Agency released the following tentative schedule of important dates for the environmental analysis and application process.
Scoping Notice Released May 1, 2025
Public Scoping Period (30+ days) May 1, 2025 – June 6, 2025
Public APC Scoping Meeting May 14, 2025
Public Scoping Summary Report End of June 2025
Release Draft EIS Late 2025
Release Final EIS Early 2026
Douglas County Action Spring 2026
Tentative Project Approval and SSAP Amendment Hearing(s) Summer 2026