City of Dowagiac: Data Center FAQ and Updates

This page has current, updated information on activities related to the site plan permit application submitted by Hyperscale Data, Inc.

Overview

The City promised to tell the community when the company that runs the data center at 415 E. Prairie Ronde Road filed a permit application. The Company filed a complete site plan permit application on Friday, November 6, 2026. This update page was published Monday, November 9, 2026, and was most recently updated on Monday, November 23, 2026. More information will be posted as it becomes available.

The City’s job now is to check that site plan permit application against the City’s rules, especially the noise ordinance Council adopted in March. If the site plan permit application meets the rules, it will be approved. If it doesn’t, it will be denied, and the Company can make changes and resubmit if it chooses to do so.

Monday, November 23, 2026 status update
In the time since this FAQ was last updated on November 17, 2026 (v2.1), information has been added and noted at the end of this page.

Review of the Company's complete site plan permit application continues. The following information has been added to this page:

Other elements of the City review, including those related to sound and stormwater, are ongoing. No decision has been made on the application. The City will keep this page updated. With the upcoming holiday closure and staff schedules, the next update will be posted on or before Monday, December 7, 2026.

Monday, November 16, 2026 status update
In the time since this FAQ was first published on November 9, 2026, information has been added throughout and noted at the end of this page.

After an initial review of the Company’s site plan permit application, City staff determined that under Dowagiac's Zoning Ordinance, the application will go through administrative review, also known as staff review. The application does not request changes that would require it to go before the Planning Commission or City Council. No decision has been made on the application.

  • The Dowagiac Public Safety team is reviewing the parts of the application that relate to fire safety and emergency response.

  • The City has retained Prein&Newhof, an engineering firm, to review the stormwater drainage plan.

  • The City Attorney has retained Soundscape Engineering, a firm of licensed engineers and architects specializing in sound, to review all parts of the application related to sound.

  • (Added November 17) A drawing of the site plan the Company submitted with its application is available here.

The City is reviewing which parts of the application can be posted publicly and will share them in a future update. The City will keep this page updated. The next update will be posted on or before Monday, November 23, 2026.

This frequently asked questions page answers common questions about what happens next, the history of the project, and which agencies are in charge of what. The City is not the only entity involved.

A note on the word “rules”: This page says "rules" to mean the City's ordinances. An ordinance is a local law passed by City Council. The zoning ordinance, the building code, and the noise ordinance are all rules in this sense.

A note on names: The City is dealing with Alliance Cloud Services, which is a subsidiary of the more commonly known Hyperscale Data, Inc. In the six years since it purchased the building in question, the Company and its affiliates have also used the names Ault Alliance, Inc. and Digital Farms LLC. To keep things simple, this page calls all of them "the Company."

1. Why is the City posting an FAQ about this site plan permit application when it doesn't do that for other similar applications?

The City does not usually post an FAQ about a site plan permit application. It is doing so here because of ongoing community feedback and strong public interest in this project. Many residents have asked questions and shared concerns about the facility and how it affects our community, now and in the future. The City wants everyone to have the same facts in one place.

2. What is this project, and where is it?

The Company runs a computer processing center, also known as a data center, in a portion of the building at 415 E. Prairie Ronde Road. The site is zoned as a Planned Unit Development, also known as a PUD, that allows for industrial use and commercial space. The Company has applied for a site plan permit to make changes on its property.

3. What is the history of this facility since its purchase by the Company?

This building has been a computer processing facility in various ways since the Company purchased it in 2020. It has also housed other commercial tenants and continues to do so.

4. What is the City's role in the site plan permit application process?

The City's job is to make sure the project follows City rules. That includes zoning rules, building rules, and the City's noise rules. If the site plan permit application meets those rules, the City issues the permit. If it does not, the City does not issue the permit.

The City does not control every part of this project. The State of Michigan and the federal government oversee matters related to water and air quality and other environmental matters. The electric power is handled by the utility, Indiana Michigan Power (I&M), an operating company of AEP. See the chart at the end of this page for more information on who handles what, along with contact information.

Laws about artificial intelligence and how it is used are outside the City's power. If you have concerns about that, contact your state and federal representatives.

5. Can the City just say no to this site plan permit application?

Not if the information in the site plan permit application follows the rules. If a project meets the City's zoning, building, and other rules, the City must issue the permit. The City cannot deny a permit only because some people oppose the project. It also cannot make up new rules just to block one business.

What the City can do is make sure rules are followed, hire its own experts to check the Company's work, and take enforcement action if City rules are broken. That is what the City is doing.

6. What has the City done about this so far?

The Company did not file a complete site plan permit application until Friday, November 6, 2026. However, the Company started issuing press releases about its plans for the facility more than a year ago. Those press releases raised questions in the community and with City leadership, so the City started preparing. A press release is not a permit application, but the City wanted to be prepared for one. Here is some of what the City has done in preparation for the site plan permit application:

  • February 2026: City Council held an educational session on data centers with Dr. Christopher Kobus of Oakland University. Dr. Kobus is an expert in energy, heat, and sustainable energy systems, including how data centers affect the environment and local infrastructure.

  • February 2026: City police took sound readings at four industrial areas, including the facility at 415 E. Prairie Ronde Road, to help set fair noise limits. The City Manager’s office also researched noise limits in several other Michigan communities to help inform guidelines.

  • March 9 and March 23, 2026: City Council held two public readings of a noise ordinance with clear decibel limits (Ordinance 2026-01) and adopted it.

  • March 26, 2026: Council members, the City Manager, and his team attended a data center information session at the Cass County Courthouse led by Dr. Sarah Mills of the University of Michigan’s Graham Sustainability Institute. Dr. Mills is the author of the report What Michigan Local Governments Should Know About Data Centers.

  • April 1, 2026: Mayor Bakeman published an open letter to the Company's CEO asking it to be more open about its plans, many of which the City learned about in the media.

  • August 10, 2026: City Council authorized the City Attorney to hire sound experts to help enforce the City's noise ordinance and plan for an eventual permit application. The City Attorney then hired Soundscape Engineering, a firm of licensed engineers and architects specializing in sound, to be ready for a permit application.

  • November 6, 2026: The City received the Company's complete site plan permit application that afternoon.

  • November 9, 2026: The City published the first version of this FAQ.

All of this happened at public meetings or was shared in public statements. Agendas and minutes are on the City website.

7. What happens next, and when?

The City's zoning administrator, the City Manager, the Assistant City Manager, and the City Attorney check to make sure the site plan permit application follows City rules. Typically, this would be handled by the zoning administrator, who is a member of the City Manager’s office, alone. However, given the size of the project and related public interest, the City is adding these additional layers of review. If the site plan permit application follows the rules, approving or denying the application is a staff decision. If the changes the Company is requesting would change its facility size by more than 10%, that approval request goes in front of the Planning Commission. If the Company asks to change the PUD or the City's rules, the approval request goes in front of both the Planning Commission and the City Council.

As noted in the November 16 update above, after an initial review of the Company's site plan permit application, City staff has determined that the application will go through administrative review. No decision has been made on the application.

Concurrently, Soundscape Engineering, a firm of licensed engineers and architects specializing in sound and hired by the City Attorney, is reviewing the sound study and plans submitted by the Company in its application.

If the application follows all City rules and doesn’t request modifications that would require it to go in front of the Planning Commission and/or City Council (see explanation above), staff will approve it. If it does not follow the rules, staff will deny it. The Company can then make modifications and resubmit if it chooses to do so.

8. Will the facility use City water or sewer?

The City runs the water and sewer utility that serves the facility at 415 E. Prairie Ronde Road. If the Company wanted to use City water to cool its equipment, the amount needed would almost certainly require a special agreement with the City utility. The Company has never applied for one, and the City has never granted one.

9. Where does the facility's electricity come from?

The facility gets its power from I&M, not from the City's electric utility. The City does not supply power to this site and has no approval power over service from I&M. Any meaningful increase in the facility's power use must be approved by the utility, I&M.

10. What about noise?

Noise is the concern the City hears most about this project. It is also the one the City has the most power over.

In March 2026, City Council added a noise section with clear decibel limits to the City's Zoning Ordinance (Section 2.27). The old rule only said noise had to be "reasonable," which was hard to legally enforce. These are the current limits for decibels, a way to measure sound. The limit that applies is set by the zone of the property receiving the sound. That means homes near the data center get the 65 and 55 decibel limits, even though the data center itself is in an industrial zone. The site plan must show that the facility will meet these limits.

  • Residential zoning: 65 decibels during the day (7 AM to 10 PM), 55 decibels at night (10 PM to 7 AM)

  • Commercial zoning: 65 decibels day and night.

  • Industrial zoning: 75 decibels day and night

The City Attorney has hired Soundscape Engineering, a firm of licensed engineers and architects specializing in sound, to review the Company's sound study and judge whether the plan will keep noise under the City's decibel limits. The City will not make a final decision on the application until it has that firm's recommendation.

11. Is the City getting money from the Company?

The Company pays property taxes on its building, like any other property owner. Other than that, the Company is a customer of the City’s water and sewer utility. The City has not given the Company a tax break or any special deal. The City is receiving standard permit fees that would apply to any similar application.

12. What about construction activity?

If the permit is approved, construction at the site must follow the same rules as any other business. City rules allow construction work between 7 AM and 10 PM. To report a violation by any company, call the Dowagiac Police Department's non-emergency line at 269.445.1560.

13. If there’s an emergency at the facility, are the Dowagiac Fire and Police Departments ready?

As part of the review process, the Dowagiac Public Safety teams are reviewing the Company’s emergency plans. They will advise on feasibility.

14. When will more information be available?

The City promised to keep the community updated on what’s going on with the Company’s permit-related activities once it received a submission. This page was originally published on Monday, November 9, 2026, one business day after a complete site plan permit application was received. An update was posted on Thursday, November 12, and a full status update was posted on Monday, November 16. It will take time to review the application in full. The next update will be posted on or before Monday, November 23, 2026.

15. Why has this taken so long?

The City first asked the Company for a complete application more than a year ago, when its press releases began to raise questions in the community. The City cannot review a project until it has a complete application. The Company turned one in on November 6, 2026.

16. Where can I get updates?

The City will continue to post new content and updates on this page on the City website. It is also messaging key updates on the City of Dowagiac Facebook and Nextdoor pages.

17. Is this application about the Company’s plans for robotics, AI, or something else?

The City does not take a company’s business plans into account when reviewing a site plan permit application, as long as all City rules and other laws are followed. A site plan permit application shows physical changes to a property, like new equipment, structures, or sound barriers. The City checks whether those changes follow City rules, the same way it would for any business.

Businesses can change what they do inside a building without a City permit, as long as the new use is allowed by the property’s zoning. For example, if a business wanted to use its property in a way the zoning does not allow, like building apartments on land zoned for industrial use, it would need to ask for a zoning change. That request goes before the Planning Commission and City Council. This application does not ask for that.

For questions about the Company’s business plans, contact the Company directly. If you have concerns about artificial intelligence and how it's used, contact your state and federal representatives.

18. But I saw on social media that...

There has been a lot of inaccurate information about this project going around, especially online. Some of the inaccurate information circulating comes from honest mistakes or misunderstandings. Some of it comes from AI summaries that get the facts partly or fully wrong.

This page is the City's official source of facts about the permit. If you see a claim that does not match what is here, check where it came from. A long statute number or the words "primary source" are not proof. Read the whole document, not one line.

If you think something on this page is wrong, tell us. Email citymanager@dowagiac.org, call 269.783.2530, or come to a City Council meeting. If the City makes a mistake through this process, it will fix it and say so.

Who handles what

Noise

Zoning, site plan, and PUD

Building and fire code

Water quality, air quality, and other environmental matters

  • Who is in charge: Michigan Department of Environment, Great Lakes, and Energy (EGLE)
  • What they do: Oversees water quality, air quality, and other environmental matters
  • Website https://www.michigan.gov/egle/contact

Electric power

  • Who is in charge: Indiana Michigan Power (I&M), an operating company of AEP
  • What they do: Supplies electric service to the facility and must approve any increase in power use
  • Learn more or contact: https://www.indianamichiganpower.com/contact/

Notes

  • Updates to this page will be made throughout the copy above. Changes will be noted in this section as new version numbers. Corrections to spelling and grammar, and updates to formatting for clarity, may not be noted.
  • Version 1.0 was published November 9, 2026.
  • Version 1.1, published November 12, 2026, added the name and URL of the licensed engineers and architects specializing in sound to Q6.
  • Version 2.0, published November 16, 2026, added a full status update to the introduction section above the FAQ and made related changes, like eliminating redundant copy. In Q7, added information on Soundscape Engineering, as well as further details on the review and approval process. In Q10, added information on Soundscape Engineering, as well as the section number of the City's Zoning Ordinance that references noise. Minor updates to copy related to timing throughout, in order to keep the full page current.
  • Version 2.1, published November 17, 2026, added the drawing of the site plan the Company submitted, and added a new Q17. Updated subsequent question numbers accordingly.
  • Version 3.0, published November 23, 2026, added a full status update to the introduction section above the FAQ. Added the Company's site plan permit application form, its EGLE permit information checklist, and its stormwater calculations. Some contact information in these documents is redacted. Minor updates to copy related to timing throughout, in order to keep the full page current.