Project is approximately 50% complete, with 299 truckloads removed
Vegetation and Debris Removal from Citywide Drainage Channels

Project is approximately 50% complete, with 299 truckloads removed

Project is approximately 50% complete, with 299 truckloads removed

  • The project is approximately 50% complete.
  • Jerry Branch
    • Crews have cleared the lower section of Jerry Branch from the north side of State Road 580 in the Ravenwood subdivision south through the outfall at Jerry Lake.
    • Jerry Branch has also been cleared from Laurelwood north to the Lynwood cul-de-sac area, as well as approximately 200 feet south from Indian Creek Court.
  • Curlew Creek
    • Curlew Creek has been cleared from the Golf Course to County Road 1.
    • Crews are currently clearing Curlew Creek from County Road 1 to Belcher Road. Two crews are working simultaneously—one beginning at Salem Court and moving east, and the other starting at Belcher Road and moving west.
    • CrowderGulf estimates project completion by late February to early March.
  • As of January 11, 2026, a total of 299 loads of debris have been hauled, equaling 15,635 cubic yards removed.