krome

Krome & Flagler Avenue Water & Sewer Upgrade & Transit Accessibility Improvements

Upgrading Critical Infrastructure and Improving Accessibility in Homestead. The City of Homestead is advancing a major infrastructure improvement project along Krome Avenue and Flagler Avenue to replace aging and undersized water and sewer mains, drainage system, and enhance transit and roadway accessibility. This multi-phase project will support reliable utility service, improve safety, and create a better experience for residents, businesses, and transit users.

Overview

Project Summary

This project includes the replacement and upgrade of water and sewer mains along Krome and Flagler Ave, as well as significant improvements to drainage system, roadway safety, and transit infrastructure. Enhancements will include updated sidewalks, lighting, landscaping, pavement markings, signalization, and the addition of bus shelters to improve accessibility and overall mobility in the area.

Project Location

The project will take place in the following areas:

  • Krome Avenue: from SW 328 Street/Lucy Street to the MDC Busway
  • Flagler Avenue: from Krome Avenue to Campbell Drive
  • Krome Avenue: from the MDC Busway to N. 4 Street

Additional Improvements

Along Krome Avenue from the MDC Busway to N. 4 Street, the project will also include:

  • Drainage System Upgrades
  • New Signing and Pavement Markings
  • Signalization Improvements
  • Sidewalk Reconstruction
  • Lighting Enhancements
  • Landscaping
  • Bus Shelters

Why This Project Matters

Investing in Reliable Infrastructure and Better Connectivity

This project is designed to upgrade essential water and sewer infrastructure while improving accessibility and roadway conditions along a key corridor in the city. These upgrades will increase system capacity, support future growth, and position Homestead for long-term sustainability. In addition, the improvements will enhance service reliability, strengthen transit amenities, and improve safety and mobility for the community.


Project Timeline

Three Phases of Construction

Phase 1: Krome Avenue: SW 328 Street/Lucy Street to Miami Dade County Busway

April 22, 2026 - April 22, 2026
The awarded contractor is expected to receive the Notice to Proceed (NTP) at the beginning of May 2026. Work in this phase will focus on water and sewer upgrades along this section of Krome Avenue.

Phase 2: Flagler Avenue: Krome Avenue to Campbell Drive

April 23, 2026 - April 23, 2026
Once Phase 1 is completed, the contractor will move to Flagler Avenue to continue water and sewer main upgrades.

Phase 3: Krome Avenue: MDC Busway to N. 5 Street

April 28, 2026 - April 28, 2026
The final phase will include water, sewer, and drainage system upgrades, as well as transit accessibility enhancements.

Important Dates

Upcoming Milestones

22
Apr 2026

Mayor and City Council awarded the construction contract

23
Apr 2026

Community Outreach

28
Apr 2026

Project kickoff meeting with contractor

29
May 2026

Contractor to receive Notice to Proceed (NTP) for Phase 1


Community Impact

Keeping Residents and Businesses Informed

This project is especially important for businesses located in the Community Redevelopment Agency area and for residents of Pioneer Village. The City is committed to proactive communication throughout construction. This is completed through several community meetings held in April and May 2026 to provide information regarding the project.

The City will continue to host additional community meetings and provide ongoing updates to keep the community informed as the project progresses.

Stay Informed

Get notified about new projects, the latest updates, and new opportunities to engage.


What to Expect

Construction Will Be Completed in Stages

Because this is a phased project, work will move from one roadway to the next over time. Residents, business owners, and visitors should expect some road and lane closures due to this much-needed utility installation and roadway reconstruction work. The City will continue sharing information to help the community plan ahead and stay informed.


District

This project is located in District 4, represented by Vice Mayor Jenifer N. Bailey.


For More Information

For more information, please contact


Current Project Status

Preliminary utility investigation work for the Krome Avenue & Flagler Avenue Water and Sewer Upgrades and Krome Avenue Transit Accessibility and Roadway Improvement Project began the week of June 1st, 2026. The contractor will continue field activities over the next several weeks to locate and verify existing underground utilities ahead of major construction.

Residents and businesses may notice roadway utility markings, exploratory digging, and field crews throughout the project area. No road closures are anticipated at this time; however, minor traffic impacts may occur near active work zones.