Project BR-26-C1 Phases
Project

Phase 1, 1A and 2

10th Ave, 11 Ave, 12th Ave, & 7th St Reconstruction (BR-26-C1)

Phasing Details (Currently Under Construction)
Phase 1 – 65 Calendar Days
Location: 7th Street South, between 10th Avenue South and 11th Avenue South

Phase 1A – 35 Calendar Days
Location: 10th Avenue South, between 7th Street South and 6th Street South

Phase 2 – 65 Calendar Days
Location: 7th Street South, between 11th Avenue South and 12th Avenue South

Please note: All timelines are subject to change based on weather conditions and unforeseen circumstances.