Fargo, ND
BR-25-B3 OVERHEAD

9th Ave S, 6th St S & 7th St S Reconstruction (BR-25-B3)

Project Location:

  • 9th Avenue South from 8th Street S to 5th Street S
  • 6th Street South from 9th Avenue S to 10th Avenue S
  • 7th Street South from 9th Avenue S to 10th Avenue S

Full roadway reconstruction including:

  • Water main replacement
  • Water service replacement (to curb stop valve)
  • Sanitary sewer main spot repairs
  • Sanitary sewer service replacement (to behind the curb)
  • New storm sewer pipe, inlets, and leads
  • Driveway Approaches (up to sidewalk)
  • Sidewalk replacement
  • Asphalt Pavement

VIEW PROJECT INFO PDF

SPECIAL ASSESSMENTS

Part of this project is funded through special assessments. To check if a parcel has a special assessment, click the following link: www.fargoparcels.com
For more special assessment information click here.

Project BR-25-B3
VIEW FULL SCREEN INTERACTIVE MAP
Cost Distribution

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Project Phases

Phase 1: 7th St S - 10th Ave S to 9th Ave S
70 days
Phase 1A: 9th Ave S - 8th St S to 7th St S
45 days
Phase 1B: 9th Ave S - 7th St S to 6th St S
45 days

Project Updates

Important Dates

7
May 2025

Bid Date

27
May 2025

Project & Phase 1 Start Date

27
Sep 2025

Substantial Completion has been met.