9th Ave S, 6th St S & 7th St S Reconstruction (BR-25-B3)
Project Location:
- 9th Avenue South from 8th Street S to 5th Street S
- 6th Street South from 9th Avenue S to 10th Avenue S
- 7th Street South from 9th Avenue S to 10th Avenue S
Full roadway reconstruction including:
- Water main replacement
- Water service replacement (to curb stop valve)
- Sanitary sewer main spot repairs
- Sanitary sewer service replacement (to behind the curb)
- New storm sewer pipe, inlets, and leads
- Driveway Approaches (up to sidewalk)
- Sidewalk replacement
- Asphalt Pavement
VIEW PROJECT INFO PDF
SPECIAL ASSESSMENTS
Part of this project is funded through special assessments. To check if a parcel has a special assessment, click the following link: www.fargoparcels.com
For more special assessment information click here.
VIEW FULL SCREEN INTERACTIVE MAP
Stay Informed
Get notified on upcoming engagements and the latest project related news.
Project Phases
Phase 1: 7th St S - 10th Ave S to 9th Ave S
70 days
Phase 1A: 9th Ave S - 8th St S to 7th St S
45 days
Phase 1B: 9th Ave S - 7th St S to 6th St S
45 days
Project Updates
7 items
9/27/2025 Project Update
Substantial Completion
8/22/2025 Project Update
Phase 1B Open for Public Use
8/13/2025 Project Update
Phase 2A Start Date
8/8/2025 Project Update
Phases 1 & 1A Open for Public Use
7/21/2025 Project Update
Phase 2 Start Date
7/7/2025 Project Update
Phase 1B Start Date
6/20/2025 Project Update
Phase 1A Start Date
Important Dates
7
May 2025
Bid Date
27
May 2025
Project & Phase 1 Start Date
27
Sep 2025