Fargo, ND
BR-26-A1 OVERHEAD

Evergreen Rd (BR-26-A1)

This project is to improve the aging infrastructure of 29th Avenue North, Evergreen Road and Longfellow Road

Project Location
29th Avenue North from Elm Street to Longfellow Road, Evergreen Road from 29th Avenue to 28th Avenue and Longfellow Road from 29th Avenue to 28th Avenue

Full roadway reconstruction including

  • Water main replacement
  • Water service replacement (to curb stop valve)
  • Sanitary sewer service replacement (to behind the curb)
  • New storm sewer main, inlets and leads
  • New driveway approaches (up to sidewalk)
  • Sidewalk replacement
  • New curb and gutter
  • New asphalt pavement
  • New street lighting

SPECIAL ASSESSMENTS

Some properties within the project area may be subject to special assessments to help fund the improvements. If you’re a property owner and would like to check whether your parcel is affected, you have two options:

  • Visit Fargo Parcels directly.
  • Or, click on a parcel in the interactive map below, then select the “Fargo Parcels” button to be taken to the corresponding property page.

Note: Estimated special assessment costs will be posted as the project gets closer to starting. These amounts stay on your property as estimates throughout the project and won’t become final until the work is completed.

Once on the Fargo Parcels site, you can:

  • Search by your address or parcel number
  • View your assessment history
  • See estimated special assessment costs related to this project (if applicable)

For more special assessment information click here.

Map Viewer

Stay Informed

Get notified on upcoming engagements and the latest project related news.

With construction planned to begin Spring 2026, all phases and dates are tentative

Phase 1A : 29th Ave from Elm St to Longfellow Road
70 days
Phase 1B : Elm St and 29th Ave intersection
21 days
Phase 2A : South half of Evergreen Rd
60 days

Important Dates

22
Oct 2025

Bid Date

3
Oct 2026

Substantial Completion Date