Hickory St N, Maple St N & 29th Ave NE Reconstruction (BR-25-E1)

Project Location:

  • 29th Ave NE from Longfellow Rd N to Lilac Ln N
  • Hickory St N from 28th Ave NE to 29th Ave NE
  • Maple St N from 28th Ave NE to 29th Ave NE

Full roadway reconstruction including:

  • Water main replacement
  • Water service replacement (to curb stop valve)
  • Sanitary sewer main spot repairs
  • Sanitary sewer service replacement (to behind the curb)
  • New storm sewer pipe, inlets, and leads
  • Driveway Approaches (up to sidewalk)
  • Sidewalk replacement
  • Asphalt Pavement

VIEW PROJECT INFO PDF

Project BR-25-B3
VIEW FULL SCREEN INTERACTIVE MAP

SPECIAL ASSESSMENTS

Part of this project is funded through special assessments. To check if a parcel has a special assessment, click the following link: www.fargoparcels.com
For more special assessment information click here.

Cost Distribution

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Project Phases

Phase 3A: 29th Ave NE - from Longefellow Rd N to 150' east of Hickory St N
2025
Phase 3B: 29th Ave NE - from 160' west of Maple St N to 200' east of Maple St N
2025
Phase 1B: Hickory St N - North half of block
2025

Project Updates

Important Dates

26
Feb 2025

Bid Date

10
Jun 2025

Start Date (Tentative)

10
Oct 2025

Substantial Completion