County Bridge Replacement | Melbourne Road Bridge | C08 Project

The work associated with the bridge itself is complete. Grading work around the bridge and on approach to the bridge is complete. Contractor is waiting for the paving subcontractor to mobilize to the site. Anticipate approach paving in early November with final completion of the project mid-November, weather permitting.