Highway F-48 W (Old Hwy 6) Resurfacing
Widening and side road base layer asphalt is complete. Interlayer aspahlt placement is in process. Asphalt surface layer, pavement marking, and roadside safety items still remain. As well as the concrete pavement replacement on both sides of the I-80 overpass. Please note, placement of asphalt surface layer will be full width, edge of shoulder to edge of shoulder, and portions of this road section will be impassable for part or most of the day. Goal would be to provide 48 hours notice prior to surfacing operation to affected property owners and businesses. Expect asphalt work to be completed by May 31st weather permitting. Concrete pavement work is tentatively scheduled for an August start with completion in September weather permitting.