Bayview Trail - Phase 0.5
Project Description
This project will construct approximately 4.7 miles of paved multi-use trail as part of Bayview Trail Phase 0.5. The trail will extend connectivity between Lake Stevens and Marysville and align with Marysville’s existing Bayview Trailhead at 64th St NE. The project is intended to expand opportunities for walking, rolling, and other outdoor recreation while improving regional connections between the two communities.
Background
Bayview Trail Phase 0.5 is a joint effort between the City of Lake Stevens and the City of Marysville to continue development of a connected multi-use trail system. The project supports both cities’ shared goal of improving outdoor recreation opportunities, encouraging active transportation, and strengthening community connectivity.
Phase 0 of the project was completed, and a ribbon-cutting ceremony was held in January 2025. For more information on that phase, visit the Bayview Trail Phase 0 project page.
project page
This phase will continue progress toward a broader trail connection between the two cities and reflects the ongoing partnership between Lake Stevens and Marysville to deliver each section of the trail. This section of the trail will extend from 12th Street SE to 8th Street SE.
Project Manager
Erik Mangold
Capital Projects Manager
Phone:
425.622.9443
Email: capitalprojects@lakestevenswa.gov
- City of Lake Stevens – Public Works & Planning, Community Development
- Design Engineer – Perteet, Inc
- Construction Contractor – TBD.
Weekly Construction Hours
- Monday – Friday 7 AM – 5 PM
The 100% plans for the trail system can be found here: 100% Bayview Trail 0.5 Plans
Project Map

Stay Informed
Get notified on upcoming engagements and the latest project related news.
Road Closure
Starting on October 26 to November 13, 2026 (tentative) along 12th Street SE between 87th Avenue SE and 89th Avenue SE.
The closure is needed to work on the Bayview Trail. Work includes removing the existing sidewalk and putting in a 10-foot multi-use path to connect the current Bayview Trail at West Lake Park to the next phase of the trail, which will extend the 10-foot-wide paved trail from 12th Street SE to 8th Street SE.
Pedestrian access will be maintained during the closure.
Questions? Contact Lake Stevens Public Works: 425-622-9403
Project Construction
Construction is underway, beginning with the pedestrian ramp connection, sidewalk removal and replacement, and the road realignment.