8th Street SE and 79th Avenue SE Corridor Safety Improvements

8th Street SE and 79th Avenue SE Corridor Safety Improvements

Project Information Project Contact
The city worked with a traffic engineering consultant to prepare a traffic safety analysis, conceptual design alternatives, and plans for roadway safety-related improvements along the corridor.

The project area spans three intersections (see below image):

- 79th Avenue SE and 10th Street SE
- 79th Avenue SE and 8th Street SE
- 83rd Avenue SE and 8th Street SE
Whitney Ojalehto, EIT, Engineering Technician
Phone: (425) 622-9453
Email: wojalehto@lakestevenswa.gov

For each segment, the consultant prepared recommendations for potential roadway/roadside safety (current phase), non-motorized accessibility (future phase), and traffic calming improvements (current and potential future phase).

Phase I of this project targets vehicle speed reduction and driver awareness by channelization and signage updates throughout the corridor, including spot-specific lane narrowing and realignments, rumble strips approaching the intersections, and updated signage. These improvements will be installed by Summer 2024. The city will repeat the traffic data collection in Fall 2024 to compare it to the baseline data. The results and analysis will refine scoping for future improvements along this corridor.

Download the design memorandum [here] and the current plans [here]


Image Description: aerial photograph of the project area. The project limits are highlighted in yellow, and the intersections are circled in white.

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Project Phases

Data Collection and Analysis
October 2023 - November 2023
Preliminary Design
December 2023 - January 2024
Final Design and Recommendations
February 2024 - March 2024