Image showing ongoing construction work at Dawsons Corner
Project

Construction

Take a look at the construction phases, and planned traffic management.

Dawsons Corner

Final road surfacing – November 2026

The Dawsons Corner and Stanningley Bypass improvement scheme is now entering its final stages, with final road surfacing taking place during November.

To complete this safely, a series of overnight lane and road closures will be needed from Monday 9 November to Sunday 29 November. Work will take place between 8pm and 5am, with roads and lanes reopening each morning. As road surfacing can be affected by poor weather, the programme may be subject to change, with contingency dates built in where required.

When will closures be in place?

9–13 November
Overnight lane closures on approaches to Dawsons Corner while we prepare the road for its final surface. Resident access will be maintained. 

12–17 November
Final surfacing begins around Dawsons Corner, with closures affecting the route towards Stanningley Bypass and the Owlcotes Lane slip road. Access to New Pudsey Station will be via Woodlands Avenue. Businesses remain open as usual. 


Where we will be working 12-17 November?

The highlighted area shows the section of road being resurfaced during this phase.

How do I get around the closures 12-17 November?


17 November
For one night, the A647 Bradford Road eastbound will be closed from Thornbury Barracks roundabout through Dawsons Corner to the Woodlands Avenue junction. Access to New Pudsey Station will be via Woodlands Avenue. 

Where we will be working 17 November?

The highlighted area shows the section of road being resurfaced during this phase.

How do I get around the closures 17 November?
18–22 November
The A647 Stanningley Bypass northbound will be closed from the Richardshaw Lane slip road to A647 Bradford Road at the Ederoyd Drive junction. Access to the Ederoyd estate will be via Galloway Lane. 

Where we will be working 18-22 November?

The highlighted area shows the section of road being resurfaced during this phase.

How do I get around the closures 18-22 November?

23–29 November
Further overnight lane closures will be required around Dawsons Corner to surface the remaining areas of the scheme. Owlcotes Lane will be closed, with access to and from New Pudsey Station via Woodlands Avenue. 
there will also be temporary access restrictions at some residential streets while surfacing takes place. 

Residents and businesses directly affected will receive separate information explaining the arrangements for their street or property. 

Where we will be working 23-29 November?

The highlighted area shows the section of road being resurfaced during this phase.

How do I get around the closures 23-29 November?

Please plan ahead

Delays are possible during the overnight closures, so please plan ahead, allow extra time and follow the signed diversion routes.

Some noise is unavoidable while surfacing takes place. Our teams will work as considerately as possible and take steps to minimise unnecessary noise.

What happens next?

Following the main surfacing programme, some additional overnight works will take place between 30 November and end of December, between 8pm and 5am, with resident access maintained. 

We will then continue with the finishing touches across the scheme, including final adjustments and tuning to the new traffic signals, landscaping and tree planting.

Thank you to residents, businesses and road users for your continued patience while we complete the final stages of the Dawsons Corner and Stanningley Bypass improvements.

Night-time works at Dawsons Corner

Night-time construction works are due to begin at Dawsons Corner from Monday 12 October as the major improvement scheme moves into its final stages. These works will help prepare the junction for final resurfacing later this year.

Over the next four weeks, work will take place between 8pm and 5am, Monday to Friday, to minimise disruption during the day.

The works will take place across the entire junction, with various lane closures required on all approaches to Dawsons Corner while the remaining islands are completed and maintenance works are carried out ahead of final surfacing.

Access to New Pudsey railway station and Owlcotes Shopping Centre will be maintained throughout the works. Some activities may be noisy, although every effort will be made to minimise disruption wherever possible.

We would like to thank residents, businesses and road users for their continued patience as work progresses towards completion.

Construction phases

Embed

Content not available

The below maps outline construction phases and traffic management.